Return to search results   -   Start a new search   -   The consultation period for this application has now closed

Planning Application: 6/2017/1495/FULL


FULL PERMISSION

Decided - Granted

Mr Mark Peacock

m.peacock@welhat.gov.uk

Ocado Ltd Gypsy Moth Avenue Hatfield AL10 9BD

Installation of an uninterrupted power supply, including 2 x containers, reinforced plinth, cable chamber and the relocation of 6 x lightning protection rods

521299

209498

  • Hatfield Villages

  • Councillor James Broach
  • Councillor Rose Grewal
  • Councillor Jane Otumunye

Hatfield

10014210535
10/07/2017
11/07/2017
08/08/2017
21/09/2017

Mr A Bledowski

Ocado Retail Limited

51-53 Great Marlborough Street London W1F 7JT

Description Distance
Employment Area 0.00
Landscape Character Area 0.00
Parish 0.00
Article 4 Direction Misc (inc Walls, Gates, Gardens) 0.00
Hatfield Aerodrome 0.00
Hertfordshire Ecological Network 0.00

Granted
22/09/2017
22/09/2017

Delegated

If any documents do not appear to be shown below, please email planning@welhat.gov.uk including the case number. We will endeavour to publish any missing items within 10 working days.

To download a selection of individual documents place a tick alongside each of the relevant rows and then click on Download selected files. To download all of the documents place a tick in the box alongside the header row and all of the files will be selected, then click on Download selected files. To view individual documents click on the File for the required row.

Select All File Description Date Uploaded
Application Form - Without Personal Information
ApplicationFormNoPersonalData.pdf (114 kb) Applicationformnopersonaldata 10/07/2017
Elevation and Floor Plans
Ocado - Hatfield- Existing Proposed Site Plan rev A.pdf (625 kb) Existing & Proposed Site Plan 10/07/2017
Elevations
Ocado - Hatfield Business Park - Proposed Elevations.pdf (682 kb) Proposed Elevations 10/07/2017
Location Plan
Ocado - Hatfield-Location Plan rev A.pdf (343 kb) Location Plan 10/07/2017
Plans
Ocado - Hatfield- Existing Proposed Parking Plan rev A.pdf (580 kb) Proposed Parking Plan 10/07/2017
Design & Access Statement
Design and Access Statement.pdf (146 kb) Design And Access Statement 10/07/2017
Consultee Response
SXP00179_Redacted.pdf (83 kb) Comment - Herts Fire & Rescue Service - Attachment - Redacted 01/08/2017
Comments.pdf (69 kb) Comment - Herts Fire & Rescue Service 01/08/2017
Ocado UPS.pdf (79 kb) Comment - Environmental Health 18/08/2017
Email-6 2017 1495 FULL - Ocado - Amendments.pdf (7 kb) Comment - Environmental Health 07/09/2017
Decision Notice PDF
Decision Notice_620171495FULL.pdf (755 kb) Decision Notice PDF 22/09/2017
Officer Report PDF
Delegated Report_620171495FULL(2).pdf (24 kb) Officer Report 22/09/2017
Noise Impact Assessment
ocado Mail - Noise issues Detailed(1).pdf (133 kb) ocado Mail - Noise issues Detailed.pdf 05/09/2017
SPTMHEF3T16FREN (1)(1).pdf (1399 kb) Power Supply specification 05/09/2017
Report
ocado Mail - Noise issues(1).pdf (128 kb) ocado Mail - Noise issues.pdf 05/09/2017
Site Notice
Site Notice_620171495FULL.pdf (86 kb) Site Notice 31/08/2017
Organisation Name Sent Reply Due Reply Received
Welwyn Hatfield Borough Council Councillor Duncan Bell 18/07/2017 08/08/2017
Welwyn Hatfield Borough Council Councillor Duncan Bell 22/09/2017
Welwyn Hatfield Borough Council Councillor Lynne Sparks 18/07/2017 08/08/2017
Welwyn Hatfield Borough Council Councillor Lynne Sparks 22/09/2017
Hatfield Town Council Jonah Anthony 18/07/2017 08/08/2017
Hatfield Town Council Jonah Anthony 22/09/2017
Herts Fire & Rescue Service Mr John Parker 22/09/2017
Herts Fire & Rescue Service Mr John Parker 18/07/2017 08/08/2017 01/08/2017
Environment Agency Natasha Smith 18/07/2017 08/08/2017
Environment Agency Natasha Smith 22/09/2017
WHBC - Public Health and Protection Public Health and Protection 22/09/2017
WHBC - Public Health and Protection Public Health and Protection 24/07/2017 14/08/2017 18/08/2017
WHBC - Public Health and Protection Public Health and Protection 05/09/2017 15/09/2017 06/09/2017
Address Date Sent Expiry Date Date Reconsulted Reconsult Expiry Date
PO BOX 255 Trafalgar Court Les Banques St. Peter Port Guernsey GY1 3QL 18/07/2017 08/08/2017
Application Number Proposal Decision Distance
6/2021/3401/MAJ Installation of 3,536 solar photovoltaic (PV) array and all associated hardware on existing roof. Granted 0
6/2019/1101/FULL Erection of an ancillary staff shop following demolition of an existing cabin building Granted 0
6/2018/2241/FULL Erection of an ancillary Vehicle Maintenance Unit to serve the existing distribution unit Granted 1
6/2016/1592/MAJ Erection of two storey, 18 bay, modular building following the removal of car park canopy Granted
S6/2010/2484/FP Installation of plantroom including transformer & generator, additional dock doors and fire escapes and installation of double deck & external goods lift Granted
S6/2009/2334/MA CONSTRUCTION OF SINGLE DECKED CAR PARK OVER EXISTING GROUND LEVEL CAR PARK AND THE USE OF LAND TO THE NORTH OF THE SITE FOR CAR PARKING TO PROVIDE 566 ADDITIONAL SPACES; LANDSCAPING AND ASSOCIATED INFRASTRUCTURE CHANGES AND PROVISION OF ADDITIONAL DISABLED PARKING BAYS IN FRONT OF THE MAIN BUILDING Approval Subject to s106
S6/2008/1650/FP RETENTION OF INNER STEEL FENCE AND OUTER TIMBER FENCE Granted
S6/2008/1758/FP INSTALLATION OF TEN AIR CONDITIONING UNITS TO ROOF Granted
S6/2007/0683/MA ERECTION OF NEW TRANSFORMER ROOM AND SCREENED STANDBY GENERATOR LOCATION ON ROOF OF EXISTING PLANT ROOM AND NEW PLANT ROOM AND SMOKING SHELTER ENLARGED AND NEW REFRIGERATION EQUIPMENT AND NEW WINDOW. Granted
S6/2007/0389/FP EXTENSION TO RELOCATE 'INBOUND OFFICE; EXTENSION TO CREATE NEW RETURNS AREA AND INSERTION OF FOUR NEW LOADING DOORS Granted
S6/2007/0338/MA ERECTION OF CUSTOMER SERVICES TEAM MEMBER FACILITY EXTENSION JOINED TO EXISTING WAREHOUSE BUILDING, OVER EXISTING LOADING DOCKS AND ERECTION OF NEW TOTEWASHER FACILITY EXTENSION JOINED TO EXISTING WAREHOUSE BUILDING, OVER EXISTING LOADING DOCKS. Granted
S6/2006/1603/MA DATA CENTRE INCLUDING PROVISION OF 2 NO. CAR PARKING SPACES LOCATED INDEPENDENTLY FROM MAIN BUILDING Granted
S6/2006/0043/FP RELOCATION OF STAFF SHOP Granted
S6/2005/0872/FP Variation of Condition 2 Attached to Outline Planning Permission S6/1999/1064/OP to Allow an Additional 5 Years for Submission of Reserved Matters (Up to 29/12/2015) Granted
S6/2005/0053/FP INSTALLATION OF 8 DOCK LEVELLERS TO REAR ELEVATION, 10 VAN LEVELLERS TO SIDE ELEVATION & CONCRETING TO REAR YARD Granted
S6/2002/0048/AD ILLUMINATED FASCIA SIGN AND TWO FREESTANDING ILLUMINATED SIGNS Granted
S6/2001/0631/DE ERECTION OF A B8 WAREHOUSE BUILDING TOTALLING 8,513 SQM INCLUDING ANCILLARY OFFICE ACCOMMODATION TOGETHER WITH ASSOCIATED CAR PARKING, GATEHOUSE, SERVICE YARDS, LANDSCAPING AND ACCESS. (RESERVED MATTERS) Granted
S6/2000/1307/DE ERECTION OF A DISTRIBUTION BUILDING (CLASS B8), TOGETHER WITH ASSOCIATED PARKING, SERVICE YARDS AND LANDSCAPING Granted
S6/1999/1064/OP DEMOLITION OF EXISTING (UNLISTED) BUILDINGS, REMOVAL OF RUNWAY AND OTHER HARD STANDING AREAS AND REDEVELOPMENT FOR THE FOLLOWING PURPOSES: AS A BUSINESS PARK COMPRISING USES WITHIN USE CLASS B1, B2, B8 AND SUI GENERIS USE; HOUSING; NEW UNIVERSITY CAMPUS (USE CLASS D1 AND D2) TO INCLUDE REPLACEMENT DE HAVILLAND SPORTS AND SOCIAL CLUB AND ASSOCIATED PLAYING FIELDS; TWO HOTELS; PRIMARY SCHOOL AND ASSOCIATED FACILITIES; DISTRICT CENTRE; WORKS OF CONVERSION TO ENABLE RECREATION USE OF EXISTING LISTED HANGAR; AVIATION HERITAGE CENTRE. TOGETHER WITH ASSOCIATED HIGHWAY, TRANSPORT AND SERVICE INFRASTRUCTURE (INCLUDING A STRATEGIC TRANSPORT CORRIDOR), LANDSCAPING AND OPEN SPACE, DIVERSION OF ELLENBROOK. MEANS OF ACCESS TO BE DETERMINED Approval Subject to s106
S6/1991/0274/FP Siting of jack-leg portakabin to provide office accommodation Granted 0

There are no NMAs associated with this application